Fire Protection Construction Measures Building 216a
January 2024:
Escape staircase: Acceptance of the test statics was carried out, notification to St. 02 was made, notification of completion was sent to the City of Cologne, feedback from the City is still expected
Lecture halls will be cleaned again at the end of January
Seminar rooms: New breakthroughs will come at the end of February, the doors will be installed by the end of March, including plastering, door guards will be installed after all doors have been installed, final painting work in April
Existing doors have already been equipped with panic locks
The cafeteria door has been repaired and is waterproof again
Attention: Any notices on windows represent a fire hazard and will be removed immediately
Contact Project Manager: Jens Harder j.harder@verw.uni-koeln.de